Question.1449 - Using a lot-for-lot ordering strategy for the following item, what is the net requirements amount in week 3? (Note: Use a lead time of one week and the gross requirements and scheduled receipts depicted below, and assume you begin with 100 units in inventory.) Week 1 2 3 4 Gross requirements 0 100 80 15 Scheduled receipts 75 0 0 0 Projected ending inventory (100) Net requirements Planned order receipts Planned order releases
Answer Below: